Construction Season is still in full swing, and several construction projects are active in the City. As a reminder, please use extreme caution when driving, biking, or walking near an active construction area. When driving, please proceed slowly and be prepared to stop when workers are present. We appreciate your patience and care in keeping our crews safe!
2200 East Main Street – Fitzgerald Apartment Building Development:
Work on the Fitzgerald Apartment Building continues with work on the exterior facing in progress. There may be temporary lane closures on Main Street to permit safe construction vehicle access. The sidewalk on the north side of Main between College Avenue and the Gateway North development will be closed, and a detour for pedestrians will be provided to the South side of Main Street between Parkview and College Avenue.
Columbia Gas Line Replacement:
A new Columbia Gas Line Replacement project is scheduled to begin the week of September 15 in the area of Euclaire Avenue, South Cassingham Avenue, Montrose Avenue and Charles Street in the blocks between Livingston Avenue and Charles Street. Notices have been mailed to residents by Columbia Gas and work is scheduled to take at least three months including the restoration of pavement, sidewalks and grass areas.
North Columbia Waterline Improvements:
Waterline installation is now complete. We have completed the final repairs for the brick curb on North Columbia and the installation of new concrete curb on Caroline Avenue will be in progress over the next 3 to 4 weeks. Resurfacing of the asphalt street pavement is tentatively scheduled for October.
There will continue to be parking restrictions on the street and temporary road closures to through traffic Monday through Friday during working hours. Caroline Avenue is closed to through traffic between N Parkview and N Columbia. Access to local residents of this block on Caroline Avenue will be permitted with the possibility of some delays depending on the work being performed each day. Please check with the workers on the project if you are trying to access a local residence and need assistance.
Stanbery Avenue Waterline Improvements:
Work is substantially complete on the water main installation. Street Resurfacing work is substantially complete. There will be some minor punch list work being completed during this time.
David H. Madison Pool Parking Lot Improvements:
We are also in the process of scheduling work on the Pool Parking Lot on the North side of Clifton Avenue to begin the week of September 15th . This work will take several months to complete and the parking lot will be closed during this time.
2025 Street Improvements
Work will continue over the next few months and current active work locations include the milling and paving of Bexley Park Road between Cassady and Remington, and Sherwood Road between Remington and Gould.
Other streets planned for repairs and resurfacing include the installation of storm sewer improvements on South Parkview Avenue north of Bryden Road, and repair and paving of the eastern portion of the Bellwood-Columbus alley between Cassingham Avenue and Stanwood Road. Pavement repairs will also be performed at various locations on East Main Street over the next month.
2025 Sidewalk Improvements
Work to remove and replace the sidewalk panels that were previously marked has begun. This year’s area includes the eastern portion of Bexley including North and South Stanwood Avenue to Gould Road north of Main and South Roosevelt Avenue to Chelsea Avenue south of Main. Work will begin in the blocks between Stanwood and Gould.