Street Projects Update – July 11, 2025

Friday, Jul 11, 2025 at 4:30 pm

Construction season is in full swing and there are several active projects in Bexley! As a reminder, please use extreme caution when driving, biking, or walking near an active construction area. When driving, please proceed slowly and be prepared to stop when workers are present. We appreciate your patience and care in keeping our crews safe!

2200 E Main Street- Fitzgerald Apartment Building Development: 
There may be temporary lane closures on Main Street and sidewalk closures on the North side of Main Street between College Avenue and the Gateway North development. A detour for pedestrians will be provided to the South side of Main Street between Parkview and College Avenue.  

Columbia Gas Line Replacement:
A new Columbia Gas Line Replacement project is slated to begin in mid-August in the area of Euclaire Avenue, S Cassingham Avenue, Montrose Avenue and Charles Street in the blocks between Livingston and Charles Street. Notices will be provided to residents by Columbia Gas later this summer, prior to the commencement of work. 

Stanbery Avenue Waterline Improvements
Work is substantially complete on the water main installation and street resurfacing. There will be some minor pavement marking and punch list work being completed during this time.

N Columbia Waterline Improvements
Work is nearing completion on the second phase for the section of water main between Maryland Avenue and N Commonwealth Park. The next phase of work from Maryland Avenue to Caroline Avenue will continue over the next two months. There will be parking restrictions on the street and temporary road closures to through traffic Monday through Friday during working hours. Access to local residents will be open from Maryland Avenue on the South end or Caroline Avenue on the north end, depending on the work being performed each day. Please check with the workers on the project if you are trying to access a local residence and need assistance.

2025 Street Improvements
Work is scheduled to begin in late July. The first work locations will be N Remington Road between Ruhl and Maryland, and Ruhl Avenue between S Cassingham and Stanwood.

2025 Sidewalk Improvements
Work is scheduled to begin in late July. This year’s area is the Eastern part of Bexley which includes N and S Stanwood Avenue to Gould Road in North and Central Bexley, and S Roosevelt Avenue to Chelsea Avenue in South Bexley. The first work location will be in Central Bexley.

Find more information on our current street projects at bexley.org/street-projects

CITY OF COLUMBUS NOTE:
The City of Columbus has started work on North Cassady Avenue that will create a lengthy traffic pattern change on Cassady Avenue north of the railroad tracks just north of Delmar. 